Heli-deck installation
48 days
Challenge

Downtime is a major challenge when operating during the monsoon period season and our client was looking for a way to reduce it.

Solution

An A-type system with a slideway was installed on a barge to enable the safe and efficient transfer of personnel onto the offshore platform. The system operated in sea states up to 3.2m Hs / 5.4m Hmax. The maintenance campaign was completed in 48 days, three weeks ahead of schedule.